Leonard St NW (Powers to Alpine) Reconstruction
In-Person Construction Preparation Meeting
Date & Time: Monday, February 24, 2025, from 2 to 3 p.m.
In Person Location:
West Grand Neighborhood Organization
754 Leonard St NW #2, Grand Rapids, MI 49504
Virtual Construction Preparation Meeting
Date & Time: Monday, February 24, 2025, from 6 to 7 p.m.
Register for the virtual meeting: here
Tentative Construction Schedule
Phase 1 – North half of Leonard St (Powers to Alpine). Eastbound traffic will be maintained. March – June 2024
Phase 2 – South half of Leonard St (Powers to Alpine). Westbound traffic will be maintained. June – August 2024
Construction Updates
The Leonard Street reconstruction project is moving along. The city expects to pave the north side of the street this Friday. Next week, contractors will raise manhole castings to be level with the new pavement and expect westbound traffic to open Friday, June 20th.
Friday, June 20th contractors will begin working on the south side of the street and eastbound traffic will close.
This schedule is dependent on the weather.