Rockford Construction has sent a construction update on the Amway Soccer Stadium to share with neighbors.
Other Rockford Construction Updates on the Stadium.
Following up on our previous communication, here are some important updates regarding upcoming Phase 1 work:
Fencing Installation
Scheduled to begin Wednesday, April 16
This work is related to the Phase 1 area noted in the previously issued flyer
The Pearl St. sidewalk south of the current Big Boy will be closed from Mt. Vernon to Summer Ave.
Parking Changes
The two parking lots east of Summer Ave will be closed to public parking
Signage will be placed at lot entrances to alert the public
Parking kiosks in those lots will be removed on Tuesday, April 15 by the City
Road Access
We are expecting to close Summer Ave. starting May 1, between Blumrich St. and Lake Michigan Dr.
Next Steps
We’ll share more information soon on upcoming impacts to roads as we continue coordination with the utility provider and the City of Grand Rapids.
Announcing some important updates regarding the utility work for the Stadium project:
Road Access
Summer Ave. will be closed starting May 19, between Blumrich St. and Lake Michigan Dr.
Starting May 15, Mt. Vernon between Douglas and Lake Michigan Dr. will be closed for (7) days to begin utility relocation activities. This closure will also include the off-ramp from 131 Southbound to Pearl St.
Reminder that the bike lane and west most drive lane on Mt. Vernon will then remain closed during the duration of construction for the stadium
Additional Information
Please reference the attached from Consumers Energy on their projects and forthcoming road impacts